Project sheet for the Mazda automotive rail terminal in Salamanca

Salamanca, Guanajuato

Automotive rail terminal for Mazda

We designed and built the terminal where Mazda loads the cars that leave its plant in Salamanca. Our scope included:

  • Design, engineering and permits.
  • Civil works, earthworks, drainage, asphalt roads and lighting.
  • Track construction, welding and stress relief.
  • Perimeter fence and railroad gate.
  • Terminal maintenance.
Client Mazda
Location Salamanca, Gto.
Year 2013
Track built 8 km
Capacity 800 cars a day in 92 Automax railcars
Sector Automotive

How the terminal was designed and built

The terminal was designed to ship 800 cars a day in 92 Automax railcars. Each track has a specific role:

  • Buffer track: holds railcars waiting to be used.
  • Receiving track and dispatch track: separate incoming railcars from outgoing ones.
  • Two loading tracks: next to the pads where the cars are loaded.
  • Repair track: to service railcars without stopping operations.

Before construction we carried out soil mechanics, environmental impact and hydrology studies, and handled the permits with CNA, SCT, Ferromex and Semarnat. The work included:

  • 300,000 m³ of earthworks and hydraulic base.
  • Two railway bridges with a 25 m span.
  • 8,000 m of ballasted track with concrete ties, elastic fasteners and welded 115RE rail.
  • 8 No. 10 turnouts and 2 No. 15 AREMA turnouts to Ferromex specification at the connection with the main line.
  • Drainage with French drains and pipes, loading pads, roads, lighting and a precast concrete wall.

Will your plant ship by rail?

See our other automotive sector projects and how we work with the Ferromex network. Tell us how many vehicles you ship and we will propose a technical assessment.

It was designed to ship 800 cars a day in 92 Automax railcars. It has a buffer track, a receiving track, a dispatch track, two loading tracks and a railcar repair track.

It required permits from CNA, SCT, Ferromex and Semarnat. Before construction we carried out soil mechanics, environmental impact and hydrology studies to support the project.

With two No. 15 AREMA turnouts to Ferromex specification on the main line. Eight No. 10 turnouts were installed inside the terminal.